On January 18, the third unit of new-generation 66,000 DWT ultra-handymax bulk carrier "UBON NAREE" built by our group's Yangzi-Mitsui Shipbuilding for Singapore shipowner was delivered and departed from the shipyard wharf.
The construction period of "UBON NAREE" was approximately 10 months, which cut massive steel plates in middle March, 2025 and completed the sea trial successfully in early December, 2025, with all test results superior to the R&D design standards.
-53c8cf2328264f7194ae11308b4210eb.jpg)
On January 15, 2026, "UBON NAREE" was successfully delivered via electronic signing.
2026.03.26
Delivery of 32,000 DWT Great Lakes Bulk Carrier "HEMUS" buil…
2026.03.16
Delivery and Departure of the fourth 75,000 DWT Oil Tanker "…
2026.02.13
Delivery and Departure of the second 50,000 DWT Oil Tanker "…
2026.02.11
Delivery of the first 83,300 DWT CABU Combination Carrier "B…
2026.02.07
Delivery of the first 9000TEU Methanol dual-fuel Container V…
2026.01.23
Successful Conclusion of 66,000 DWT Bulk Carrier built by Ya…
2026.01.19
Delivery of 66,000 DWT bulk carrier "UBON NAREE" built by Ya…
2026.01.13
Delivery and Departure of 50,000 DWT Oil Tanker "DELOS T" bu…
2026.01.12
Delivery and Departure of 50,000 DWT Oil Tanker “PAROS STAR…
2026.01.11
Delivery and Departure of 114,000 DWT Oil Tanker "LUCKNAM" b…